Risk & Contingency Management for Major Infrastructure Projects
Risk and contingency management for major infrastructure projects and construction quantifies schedule and cost uncertainty — quantitative schedule risk analysis (QSRA), Monte Carlo cost risk, P50/P90 contingency setting and drawdown governance. Pioticon integrates risk with planning, cost and governance so contingency is realistic and decisions are made in time.

Key Features
Risk Intelligence Framework & Control Integration
Advantages
Value Delivered Through Active Risk Management
Our Clients
Clients Across Infrastructure & Major Programs










Testimonials
Client Narratives Validate Our Structural Governance Model.
FAQs
Frequently asked questions
What is quantitative schedule risk analysis (QSRA)?
A Monte Carlo simulation of the schedule with duration uncertainty and risk events applied, giving a probability distribution of completion dates and the risk drivers behind it.
What do P50 and P90 mean?
The completion date or cost with a 50% and 90% probability of being achieved; the gap between them sizes the contingency.
How much contingency should a major infrastructure project hold?
Enough to cover the P-level the owner has chosen (commonly P80–P90 for budget approval) less risk already treated; the number comes from the quantitative risk analysis, not a percentage rule of thumb.
Reach Us
